To prepare a rate analysis for 1 cubic meter (1m3) of concrete with a mix ratio of 1:3:6, follow these steps:
1. Calculate Quantities:
- Determine the quantities of materials required for 1m3 of concrete in the given mix ratio (1:3:6). This means 1 part cement, 3 parts sand, and 6 parts coarse aggregates.
2. Material Costs:
- Obtain current prices of cement, sand, and coarse aggregates from local suppliers or market sources.
- Multiply the quantities of each material by their respective unit costs to calculate material costs.
3.Labor Costs
- Estimate the labor required for mixing, placing, and finishing 1m3 of concrete. This can vary based on local labor rates and the efficiency of the workforce.
4.Equipment Costs
- Consider any equipment required for mixing and transporting the concrete, such as concrete mixers and wheelbarrows. Estimate equipment costs based on rental rates or ownership expenses.
5. Overhead Costs:
- Account for indirect costs like transportation, site preparation, water, electricity, and other incidentals.
6. Add Margins:
- Apply profit margin and contingency to the total cost to cover unforeseen expenses and profit.
7. Total Cost:
- Sum up the costs of materials, labor, equipment, overheads, and margins to get the total cost for 1m3 of concrete.